Reflecting on Process Capability Index (Cp) and Capability Performance Index (Cpk)

How can we calculate the Cp and Cpk of a process based on its specifications and performance?

Given an order processing operation with a specification of 4.0 hours + or - 1.0 hours, a process mean of 4.2 hours, and a standard deviation of 0.25 hours, what are the Cp and Cpk values?

Calculating Cp and Cpk

The Cp and Cpk for the order processing operation are calculated using its specifications, process mean, and standard deviation. The calculated Cp is 1.33 and the Cpk is 1.07, so the correct answer is D) 1.33, 1.07.

Understanding Cp and Cpk Calculation

The question involves determining the Capability Index (Cp) and the Capability Performance Index (Cpk) for a process by considering its specifications, process mean, and standard deviation.

To calculate the Cp, we use the formula (USL - LSL) / (6 * standard deviation), where USL is the upper specification limit and LSL is the lower specification limit. In this case, with USL = 5.0 hours and LSL = 3.0 hours, the Cp is calculated as (5.0 - 3.0) / (6 * 0.25) = 1.33.

For Cpk, we need to find the minimum of [(USL - process mean) / (3 * standard deviation)] and [(process mean - LSL) / (3 * standard deviation)]. This results in a Cpk value of 1.07.

Therefore, the Cp and Cpk values provide insights into the capability and performance of the process in meeting the specified requirements. These indices help in assessing the process quality and identifying any potential areas for improvement.

← Understanding record of duty status for commercial drivers How to conduct effective market research →